The Arlington – Construction Programme, Week 3 (15–21 October 2018)
The day-by-day, shift-by-shift working programme for The Arlington's third week, 15 to 21 October 2018, when seventeen more people started on site, the Tower A excavation was finished and Tower B begun, the first concrete came through Leila Grantley's portal for the Tower A blinding, and the membrane and reinforcement went in for the first foundation mat. It records who was on site each day, who started, who was on a rest day, and what each person was doing on each shift.
The day-by-day, shift-by-shift working programme for The Arlington in Project Week 3, Monday 15 to Sunday 21 October 2018: the week seventeen more people started on site, the Tower A excavation was finished and Tower B begun, the first concrete came through a portal for the Tower A blinding, and the membrane and reinforcement went in for the Tower A foundation mat. Each row is one piece of work on one day, in one place, by the people named, and each row is written up as its own event. Anyone not listed on a shift was not working.
How to read the programme
- Shifts: Shift A 06:00–14:00 (Percy Riall), Shift B 14:00–22:00 (Cary Parsons), Shift C 22:00–06:00 (Jake Boyd). Day means management, design, planning and office staff, 07:00–17:00. A Shift C row belongs to the date on which the shift starts.
- Starting on site: each new starter began with a site induction from Marcus Torres (Shift A) or Sarah Chen (Shift B and Shift C) before joining their crew. From this week Grace Asante is the safety officer on Shift C.
- Rest days: everyone works six shifts in seven, with rest days given week by week around the work. This week everyone who started before 15 October took a rest day; the seventeen who started on 15 October take their first in Week 4.
- Cover: when a shift supervisor was on a rest day, Fyodor Das ran the shift in their place.
- Places: the plot is the whole site in District 8. The Drop Zone is the open ground near the portals, separate from them, where deliveries from Earth were set down and received, about three kilometres from the site. The Astra Grantley portal is Leila Grantley's portal, where the concrete line comes through into Bixbus Concrete Supply's hopper. The haul route is the road across Bixbus between the portal and the site.
- Bixbus Concrete Supply crew are not part of The Arlington's workforce and are not counted in the numbers on site, but their work for The Arlington is recorded here.
- Times within a shift are approximate unless stated.
On site during the week
| Date | On site | Starting on site | Rest day |
| Mon 15 Oct | 49 | Olivia Santos, Kenneth Richards, Andrei Volkov, Dmitri Sokolov, Marco Bianchi, Rashid Khalil (Shift A); Jorge Ramirez, Toshiro Yamamoto, Marcus Oluwaseun, Hassan Mohammed, Igor Volkov, Johann van der Merwe, Nguyen Thanh, Kofi Adebayo (Shift B); Giovanni Esposito, Piotr Nowak, Grace Asante (Shift C) | Drakon Niemec, Gordan Adamson, Joel Watson, Bjorn Andersson, Jonas Hansen, Miguel Hernandez |
| Tue 16 Oct | 50 | – | Aldo Heikki, Peter Mahoney, Samuel Mensah, Jed Quintero, Jake Boyd |
| Wed 17 Oct | 50 | – | Thomas Fitzgerald, Graham Andaluse, Hernando Rodriguez, Winston Obadele, Rangi Parata |
| Thu 18 Oct | 48 | – | Samantha Greenfield, Benny Wong, Guy Barton, Brad Woodham, John Slate, Cary Parsons, Jonathan Burgess |
| Fri 19 Oct | 48 | – | Alex Markov, Baharata Goretti, Percy Riall, Carlos Mendoza, Sarah Chen, Gus Luciano, Rajesh Kumar |
| Sat 20 Oct | 49 | – | Archibald Beulen, Fyodor Das, Barry Zigmund, Marcus Torres, Ahmed Khalil, Dmitri Volkov |
| Sun 21 Oct | 53 | – | Ben Clarke, Jack Riley |
Crews this week
| Shift | Work | People |
| Day | Management, design, planning, records, quality, logistics | Archibald Beulen, Samantha Greenfield, Thomas Fitzgerald, Aldo Heikki, Drakon Niemec, Baharata Goretti, Alex Markov, Ben Clarke, Fyodor Das, Gordan Adamson, Graham Andaluse, Barry Zigmund |
| Shift A | Supervision and safety | Percy Riall, Marcus Torres |
| Shift A | Excavation | Guy Barton, Jack Riley, Winston Obadele, Samuel Mensah |
| Shift A | Survey, civil, testing | Benny Wong, Carlos Mendoza, Hernando Rodriguez, Peter Mahoney, Olivia Santos |
| Shift A | Concrete, rebar and formwork, Tower A | Brad Woodham, Joel Watson, John Slate, Kenneth Richards, Andrei Volkov, Bjorn Andersson, Dmitri Sokolov |
| Shift A | Waterproofing | Marco Bianchi, Rashid Khalil |
| Shift B | Supervision and safety | Cary Parsons, Sarah Chen |
| Shift B | Excavation | Gus Luciano, Rajesh Kumar, Jed Quintero |
| Shift B | Concrete, rebar and formwork | Jorge Ramirez, Toshiro Yamamoto, Marcus Oluwaseun, Hassan Mohammed, Jonathan Burgess, Igor Volkov, Kofi Adebayo (pump) |
| Shift B | Waterproofing, survey, power | Johann van der Merwe, Nguyen Thanh, Jonas Hansen, Ahmed Khalil |
| Shift C | Supervision and safety | Jake Boyd, Grace Asante |
| Shift C | Excavation, rebar, receiving | Dmitri Volkov, Miguel Hernandez, Piotr Nowak, Giovanni Esposito, Rangi Parata |
Monday 15 October 2018
Rest day: Drakon Niemec, Gordan Adamson, Joel Watson, Bjorn Andersson, Jonas Hansen, Miguel Hernandez.
| Time | Where | What | Who |
| 06:00–08:00 | First site office | Starters' induction | Olivia Santos, Kenneth Richards, Andrei Volkov, Dmitri Sokolov, Marco Bianchi, Rashid Khalil; inducted by Marcus Torres |
| 06:00–14:00 | Tower A footprint | Excavation: the last third of the Tower A dig | Guy Barton, Jack Riley, Winston Obadele, Samuel Mensah |
| 06:00–14:00 | Tower A footprint | Level checks | Benny Wong, Carlos Mendoza |
| 06:00–14:00 | Tower A footprint | Sump pumping; check the shoring along the deep edges | Hernando Rodriguez, Peter Mahoney |
| 08:00–14:00 | Laydown area 2 | Pre-tie the bottom mat cages | Brad Woodham, John Slate, Kenneth Richards, Andrei Volkov |
| 08:00–14:00 | Laydown area 2 | Mat edge formwork panels | Dmitri Sokolov |
| 08:00–14:00 | Laydown area 1 | Inspect the membrane rolls and plan the laying sequence | Marco Bianchi, Rashid Khalil |
| 08:00–14:00 | Testing room cabin | Set up the testing room: slump cone, cube moulds, curing tank | Olivia Santos, Barry Zigmund |
| 06:00–14:00 | The plot | Supervision; safety | Percy Riall, Marcus Torres |
| 10:00–12:00 | Astra Grantley portal | Plan the first concrete deliveries through the portal: the blinding on Wednesday and the Tower A mat on Monday 22 October | Samantha Greenfield, Fyodor Das, Leila Grantley, Teodora Ilieva |
| 07:00–17:00 | The plot | Site walk and management | Archibald Beulen |
| 07:00–17:00 | First site office | Worker files for the seventeen starters | Thomas Fitzgerald |
| 07:00–17:00 | First site office | Programme | Aldo Heikki |
| 07:00–17:00 | First site office | Rebar inspection plan for the Tower A mat | Baharata Goretti |
| 07:00–17:00 | Tower A footprint | Excavation monitoring | Alex Markov |
| 07:00–17:00 | Drop Zone | Daytime deliveries, including the site concrete pump | Ben Clarke |
| 07:00–17:00 | The plot | A third welfare cabin and more drinking water for fifty-five | Graham Andaluse |
| 13:30–14:00 | First site office | A word of welcome to the starters at the A/B handover | Archibald Beulen, with the Shift A and Shift B starters |
| 14:00–16:00 | First site office | Starters' induction | Jorge Ramirez, Toshiro Yamamoto, Marcus Oluwaseun, Hassan Mohammed, Igor Volkov, Johann van der Merwe, Nguyen Thanh, Kofi Adebayo; inducted by Sarah Chen |
| 14:00–22:00 | Tower A footprint | Rip and push spoil | Gus Luciano, Rajesh Kumar, Jed Quintero |
| 16:00–22:00 | Laydown area 2 | Pre-tie the bottom mat cages | Jorge Ramirez, Toshiro Yamamoto, Marcus Oluwaseun, Hassan Mohammed, Jonathan Burgess |
| 16:00–22:00 | Laydown area 2 | Mat edge formwork panels | Igor Volkov |
| 16:00–22:00 | Laydown area 1 | Inspect the membrane rolls | Johann van der Merwe, Nguyen Thanh |
| 16:00–22:00 | Tower A footprint | Set up the site concrete pump at the Tower A edge | Kofi Adebayo |
| 14:00–22:00 | Testing room cabin | Power and lighting to the testing room and the third welfare cabin | Ahmed Khalil |
| 14:00–22:00 | The plot | Supervision; safety | Cary Parsons, Sarah Chen |
| 21:00–22:00 | First site office | Starters' induction | Giovanni Esposito, Piotr Nowak, Grace Asante; inducted by Sarah Chen |
| 22:00–06:00 | Tower A footprint | Trim the last of the Tower A formation, with Jake Boyd acting as banksman | Dmitri Volkov, Jake Boyd |
| 22:00–06:00 | Laydown area 2 | Pre-tie the bottom mat cages under lights | Piotr Nowak, Giovanni Esposito |
| 22:00–06:00 | The plot | First night safety walk | Grace Asante |
| 22:00–06:00 | Drop Zone | Night deliveries | Rangi Parata |
Tuesday 16 October 2018 – Tower A excavation complete
Rest day: Aldo Heikki, Peter Mahoney, Samuel Mensah, Jed Quintero, Jake Boyd. Fyodor Das runs Shift C.
| Time | Where | What | Who |
| 06:00–11:00 | Tower A footprint | The last of the Tower A excavation reaches formation level | Guy Barton, Jack Riley, Winston Obadele |
| 06:00–11:00 | Tower A footprint | Final level survey of the formation | Benny Wong, Carlos Mendoza |
| 11:00–13:00 | Tower A footprint | Final formation and shoring inspection: passed | Barry Zigmund, Alex Markov, Hernando Rodriguez, Baharata Goretti |
| 11:00–14:00 | Tower B footprint | Move the excavator to Tower B and set up for the dig | Guy Barton, Jack Riley, Winston Obadele |
| 11:00–14:00 | Tower B footprint | Check the Tower B excavation set-out | Benny Wong, Carlos Mendoza |
| 06:00–14:00 | Laydown area 2 | Pre-tie cages | Brad Woodham, Joel Watson, John Slate, Kenneth Richards, Andrei Volkov |
| 06:00–14:00 | Laydown area 2 | Edge formwork panels | Bjorn Andersson, Dmitri Sokolov |
| 06:00–14:00 | Laydown area 1 | Cut membrane to length for the Tower A mat | Marco Bianchi, Rashid Khalil |
| 06:00–14:00 | Testing room cabin | Calibrate the testing equipment; write the concrete test log | Olivia Santos |
| 06:00–14:00 | The plot | Supervision; safety | Percy Riall, Marcus Torres |
| 13:30–14:30 | First site office | Marcus Torres introduces the heat-stress rules at the A/B handover: a rest in the shade every hour, water at every work face, and no heavy work between 11:00 and 15:00 | Marcus Torres, Percy Riall, Cary Parsons, Sarah Chen, with everyone on Shift A and Shift B |
| 07:00–17:00 | Astra Grantley portal | Set up the holding hopper and the line connection beside the portal | Teodora Ilieva, Femi Oyelaran, Ruairi Doyle, Valentina Cruz, Tevita Fifita, Bilal Qureshi |
| 07:00–17:00 | The plot | Site walk and management | Archibald Beulen |
| 07:00–17:00 | First site office | Costs and progress | Samantha Greenfield |
| 07:00–17:00 | First site office | Records and daily diary | Thomas Fitzgerald, Gordan Adamson |
| 07:00–17:00 | First site office | Core and Level 1 drawings | Drakon Niemec |
| 07:00–17:00 | Drop Zone | Daytime deliveries | Ben Clarke |
| 07:00–17:00 | The plot | Welfare, water and power | Graham Andaluse |
| 07:00–13:00 | First site office | Orders and costs | Fyodor Das |
| 14:00–22:00 | Tower A footprint | Trim and compact the formation for the blinding | Gus Luciano, Rajesh Kumar |
| 14:00–22:00 | Tower A footprint | Set out the blinding levels | Jonas Hansen |
| 14:00–22:00 | Tower A footprint | Lay the pump line into the excavation and test the pump on water | Kofi Adebayo |
| 14:00–22:00 | Laydown area 2 | Pre-tie cages | Jorge Ramirez, Toshiro Yamamoto, Marcus Oluwaseun, Hassan Mohammed, Jonathan Burgess |
| 14:00–22:00 | Laydown area 2 | Edge formwork panels | Igor Volkov |
| 14:00–22:00 | Laydown area 1 | Cut membrane to length | Johann van der Merwe, Nguyen Thanh |
| 14:00–22:00 | Tower A footprint | Floodlights around the Tower A excavation | Ahmed Khalil |
| 14:00–22:00 | The plot | Supervision; safety | Cary Parsons, Sarah Chen |
| 22:00–06:00 | The plot | Runs Shift C in place of Jake Boyd | Fyodor Das |
| 22:00–06:00 | Tower B footprint | Cut the edges of the Tower B dig | Dmitri Volkov, Miguel Hernandez |
| 22:00–06:00 | Laydown area 2 | Pre-tie cages | Piotr Nowak, Giovanni Esposito |
| 22:00–06:00 | The plot | Safety walk | Grace Asante |
| 22:00–06:00 | Drop Zone | Night deliveries | Rangi Parata |
Wednesday 17 October 2018 – First concrete through the portal; Tower B excavation begins
Rest day: Thomas Fitzgerald, Graham Andaluse, Hernando Rodriguez, Winston Obadele, Rangi Parata. Kofi Adebayo works Shift A today for the pour. No night deliveries are booked.
| Time | Where | What | Who |
| 05:30–06:00 | Astra Grantley portal | Leila Grantley opens her portal onto the Killerton batching yard; the line is run through and connected to the hopper | Leila Grantley, Teodora Ilieva, Ruairi Doyle, Tevita Fifita |
| 06:00–08:30 | Astra Grantley portal | The first concrete from Earth fills the hopper; the trucks load in turn | Leila Grantley, Teodora Ilieva, Ruairi Doyle, Tevita Fifita |
| 08:30–09:15 | Astra Grantley portal | The line is disconnected and the portal closed while the trucks draw down the hopper | Leila Grantley, Teodora Ilieva, Ruairi Doyle, Tevita Fifita |
| 09:15–10:30 | Astra Grantley portal | Second opening; the last of the blinding concrete | Leila Grantley, Teodora Ilieva, Ruairi Doyle, Tevita Fifita |
| 06:15–11:00 | Haul route | Four mixer trucks shuttle the blinding concrete across Bixbus. Kiran Desai takes a wrong turn through the tent streets on the first run and arrives forty minutes behind the others | Dwayne Hollis, Marta Szymanska, Kiran Desai, Lucas Ferreira |
| 07:00–11:00 | Astra Grantley portal | Fleet checks between runs | Femi Oyelaran |
| 06:45–11:30 | Tower A footprint | Pour the blinding across the Tower A formation, about 150 m³ | Brad Woodham, Kofi Adebayo, Kenneth Richards, Andrei Volkov, Samuel Mensah |
| 06:45–11:30 | Tower A footprint | Slump test every truck; cast the first test cubes | Olivia Santos |
| 06:45–11:30 | Tower A footprint | Watch the first portal concrete go in | Barry Zigmund, Baharata Goretti |
| 11:30–14:00 | Tower A footprint | Cover the blinding and start curing | Kenneth Richards, Andrei Volkov, Samuel Mensah |
| 11:30–14:00 | Tower A footprint | Wash out the pump and the line | Kofi Adebayo |
| 06:00–11:00 | Tower B footprint | Tower B excavation begins | Guy Barton, Jack Riley |
| 11:00–14:00 | Tower B footprint | Loading and trimming only | Guy Barton, Jack Riley |
| 06:00–14:00 | Tower B footprint | Level checks | Benny Wong, Carlos Mendoza |
| 06:00–14:00 | Tower A footprint | Sump and drainage around the blinding | Peter Mahoney |
| 06:00–14:00 | Laydown area 2 | Pre-tie cages | Joel Watson, John Slate |
| 06:00–14:00 | Laydown area 2 | Edge formwork panels | Bjorn Andersson, Dmitri Sokolov |
| 06:00–14:00 | Laydown area 1 | Prepare the membrane edges and primer | Marco Bianchi, Rashid Khalil |
| 06:00–14:00 | The plot | Supervision; safety | Percy Riall, Marcus Torres |
| 07:00–17:00 | The plot | Site walk; watches the first portal concrete arrive | Archibald Beulen |
| 07:00–17:00 | First site office | Costs and progress | Samantha Greenfield |
| 07:00–17:00 | First site office | Records and daily diary | Gordan Adamson |
| 07:00–17:00 | First site office | Programme | Aldo Heikki |
| 07:00–17:00 | First site office | Core and Level 1 drawings | Drakon Niemec |
| 07:00–17:00 | Tower B footprint | Excavation monitoring | Alex Markov |
| 07:00–17:00 | Drop Zone | Daytime deliveries | Ben Clarke |
| 07:00–17:00 | First site office | Orders and costs; the delay on the haul route | Fyodor Das |
| 14:00–22:00 | Tower B footprint | Rip and push spoil | Gus Luciano, Rajesh Kumar, Jed Quintero |
| 14:00–22:00 | Tower A footprint | Keep the blinding wet and covered | Toshiro Yamamoto, Marcus Oluwaseun |
| 14:00–22:00 | Laydown area 2 | Pre-tie cages | Jorge Ramirez, Hassan Mohammed, Jonathan Burgess |
| 14:00–22:00 | Laydown area 2 | Edge formwork panels | Igor Volkov |
| 14:00–22:00 | Laydown area 1 | Prepare the membrane edges | Johann van der Merwe, Nguyen Thanh |
| 14:00–22:00 | Tower B footprint | Level checks | Jonas Hansen |
| 14:00–22:00 | Tower B footprint | Temporary lighting around the Tower B dig | Ahmed Khalil |
| 14:00–22:00 | The plot | Supervision; safety | Cary Parsons, Sarah Chen |
| 22:00–06:00 | Tower B footprint | Excavation under lights | Dmitri Volkov, Miguel Hernandez |
| 22:00–06:00 | Laydown area 2 | Pre-tie cages | Piotr Nowak, Giovanni Esposito |
| 22:00–06:00 | The plot | Supervision; safety | Jake Boyd, Grace Asante |
Thursday 18 October 2018 – Membrane goes down on Tower A
Rest day: Samantha Greenfield, Benny Wong, Guy Barton, Brad Woodham, John Slate, Cary Parsons, Jonathan Burgess. Fyodor Das runs Shift B; Carlos Mendoza leads the Shift A survey; Kenneth Richards leads the Shift A concrete crew. No excavation on Tower B on Shift A.
| Time | Where | What | Who |
| 06:00–14:00 | Tower A footprint | Lay the waterproofing membrane on the blinding, working from the east bay | Marco Bianchi, Rashid Khalil, Winston Obadele, Samuel Mensah |
| 06:00–14:00 | Tower A footprint | Survey the blinding levels | Carlos Mendoza |
| 06:00–14:00 | Tower B footprint | Clear the Tower B spoil and build the ramp into the dig | Jack Riley |
| 06:00–14:00 | Tower A footprint | Sump and drainage | Peter Mahoney, Hernando Rodriguez |
| 06:00–14:00 | Laydown area 2 | Pre-tie cages | Joel Watson, Kenneth Richards, Andrei Volkov |
| 06:00–14:00 | Laydown area 2 | Edge formwork panels | Bjorn Andersson, Dmitri Sokolov |
| 06:00–14:00 | Testing room cabin | Crush the first blinding cubes; plan the test regime for the mat pour with Barry Zigmund | Olivia Santos, Barry Zigmund |
| 06:00–14:00 | The plot | Supervision; safety | Percy Riall, Marcus Torres |
| 07:00–17:00 | The plot | Site walk and management | Archibald Beulen |
| 07:00–17:00 | First site office | Records and daily diary | Thomas Fitzgerald, Gordan Adamson |
| 07:00–17:00 | First site office | Pour plan for the Tower A mat | Aldo Heikki |
| 07:00–17:00 | First site office | Core and Level 1 drawings | Drakon Niemec |
| 07:00–17:00 | First site office | Mat reinforcement details | Baharata Goretti |
| 07:00–17:00 | Tower B footprint | Excavation monitoring | Alex Markov |
| 07:00–17:00 | Drop Zone | Daytime deliveries, including more rebar for the top mat | Ben Clarke |
| 07:00–17:00 | The plot | Welfare, water and power | Graham Andaluse |
| 07:00–13:00 | First site office | Orders and costs | Fyodor Das |
| 14:00–22:00 | The plot | Runs Shift B in place of Cary Parsons | Fyodor Das |
| 14:00–22:00 | Tower A footprint | Lay the waterproofing membrane | Johann van der Merwe, Nguyen Thanh, Jed Quintero |
| 14:00–22:00 | Tower B footprint | Rip and push spoil | Gus Luciano, Rajesh Kumar |
| 14:00–22:00 | Tower A footprint | Plan the pump lines for the mat pour: one working, one standby | Kofi Adebayo, Jorge Ramirez |
| 14:00–22:00 | Laydown area 2 | Pre-tie cages | Toshiro Yamamoto, Marcus Oluwaseun, Hassan Mohammed |
| 14:00–22:00 | Laydown area 2 | Edge formwork panels | Igor Volkov |
| 14:00–22:00 | Tower B footprint | Level checks | Jonas Hansen |
| 14:00–22:00 | Tower A footprint | Power for the concrete pump | Ahmed Khalil |
| 14:00–22:00 | The plot | Safety walk | Sarah Chen |
| 22:00–06:00 | Tower B footprint | Excavation under lights | Dmitri Volkov, Miguel Hernandez |
| 22:00–06:00 | Laydown area 2 | Pre-tie cages | Piotr Nowak, Giovanni Esposito |
| 22:00–06:00 | Drop Zone | Night deliveries | Rangi Parata |
| 22:00–06:00 | The plot | Supervision; safety | Jake Boyd, Grace Asante |
Friday 19 October 2018 – Reinforcement begins on the Tower A mat
Rest day: Alex Markov, Baharata Goretti, Percy Riall, Carlos Mendoza, Sarah Chen, Gus Luciano, Rajesh Kumar. Fyodor Das runs Shift A; Cary Parsons covers safety on Shift B. No excavation on Tower B on Shift B.
| Time | Where | What | Who |
| 06:00–11:00 | Tower A footprint | Finish the membrane | Marco Bianchi, Rashid Khalil |
| 09:00–11:00 | Tower A footprint | Vacuum test the membrane seams: two seams fail and are welded again | Olivia Santos, Barry Zigmund, Marco Bianchi, Rashid Khalil |
| 11:00–14:00 | Tower A footprint | Lay the protection boards over the membrane | Marco Bianchi, Rashid Khalil, Winston Obadele |
| 11:00–14:00 | Tower A footprint | Start placing the bottom mat reinforcement from the east bay | Brad Woodham, Joel Watson, John Slate, Kenneth Richards, Andrei Volkov |
| 06:00–11:00 | Laydown area 2 | Pre-tie cages | Brad Woodham, Joel Watson, John Slate, Kenneth Richards, Andrei Volkov |
| 06:00–14:00 | Tower A footprint | Set the edge formwork around the mat | Bjorn Andersson, Dmitri Sokolov |
| 06:00–11:00 | Tower B footprint | Excavation | Guy Barton, Jack Riley, Samuel Mensah |
| 11:00–14:00 | Tower B footprint | Loading and trimming | Guy Barton, Jack Riley, Samuel Mensah |
| 06:00–14:00 | Tower B footprint | Level checks | Benny Wong |
| 06:00–14:00 | Tower A footprint | Sump and drainage | Peter Mahoney, Hernando Rodriguez |
| 06:00–14:00 | The plot | Runs Shift A in place of Percy Riall | Fyodor Das |
| 06:00–14:00 | The plot | Safety walk | Marcus Torres |
| 07:00–17:00 | The plot | Site walk and management | Archibald Beulen |
| 07:00–17:00 | First site office | Costs and progress | Samantha Greenfield |
| 07:00–17:00 | First site office | Records and daily diary | Thomas Fitzgerald, Gordan Adamson |
| 07:00–17:00 | First site office | Core and Level 1 drawings | Drakon Niemec |
| 07:00–17:00 | Drop Zone | Daytime deliveries | Ben Clarke |
| 07:00–17:00 | The plot | Welfare, water and power | Graham Andaluse |
| 11:00–17:00 | First site office | Quality records for the membrane | Barry Zigmund |
| 13:30–15:00 | First site office | Mat pour planning meeting at the handover: truck numbers, portal openings, pump lines, testing, who works which hours on Monday | Aldo Heikki, Samantha Greenfield, Brad Woodham, Jorge Ramirez, Kofi Adebayo, Olivia Santos, Teodora Ilieva |
| 07:00–13:30 | First site office | Pour plan | Aldo Heikki |
| 14:00–22:00 | Tower A footprint | Place the bottom mat reinforcement | Jorge Ramirez, Toshiro Yamamoto, Marcus Oluwaseun, Hassan Mohammed, Jonathan Burgess |
| 14:00–22:00 | Tower A footprint | Membrane upstands at the mat edges | Johann van der Merwe, Nguyen Thanh |
| 14:00–22:00 | Tower A footprint | Edge formwork | Igor Volkov |
| 15:00–22:00 | Tower A footprint | Set the standby pump line | Kofi Adebayo, Jed Quintero |
| 14:00–22:00 | Tower B footprint | Level checks; mark the Tower B formation | Jonas Hansen |
| 14:00–22:00 | Tower A footprint | Lighting for the mat pour | Ahmed Khalil |
| 14:00–22:00 | The plot | Supervision; safety | Cary Parsons |
| 22:00–06:00 | Tower A footprint | Place the bottom mat reinforcement under lights | Piotr Nowak, Giovanni Esposito |
| 22:00–06:00 | Tower B footprint | Excavation under lights | Dmitri Volkov, Miguel Hernandez |
| 22:00–06:00 | Drop Zone | Night deliveries | Rangi Parata |
| 22:00–06:00 | The plot | Supervision; safety | Jake Boyd, Grace Asante |
Saturday 20 October 2018
Rest day: Archibald Beulen, Fyodor Das, Barry Zigmund, Marcus Torres, Ahmed Khalil, Dmitri Volkov. Percy Riall covers safety on Shift A. No excavation on Tower B on Shift C; Miguel Hernandez joins the night rebar crew.
| Time | Where | What | Who |
| 06:00–14:00 | Tower A footprint | Bottom mat reinforcement across the whole footprint | Brad Woodham, Joel Watson, John Slate, Kenneth Richards, Andrei Volkov |
| 06:00–14:00 | Tower A footprint | Edge formwork complete; check it line and level | Bjorn Andersson, Dmitri Sokolov, Benny Wong |
| 06:00–14:00 | Tower A footprint | Seal the membrane around the pump-line sleeves and starter bars | Marco Bianchi, Rashid Khalil |
| 06:00–11:00 | Tower B footprint | Excavation | Guy Barton, Jack Riley, Winston Obadele, Samuel Mensah |
| 11:00–14:00 | Tower B footprint | Loading and trimming | Guy Barton, Jack Riley, Winston Obadele, Samuel Mensah |
| 06:00–14:00 | Tower B footprint | Level checks | Carlos Mendoza |
| 06:00–14:00 | Tower A footprint | Sump and drainage; clean the formation edges | Peter Mahoney, Hernando Rodriguez |
| 06:00–14:00 | Testing room cabin | Prepare the cube moulds and test sheets for Monday's pour | Olivia Santos |
| 06:00–14:00 | The plot | Supervision; safety | Percy Riall |
| 07:00–17:00 | First site office | Costs and progress | Samantha Greenfield |
| 07:00–17:00 | First site office | Records and daily diary | Thomas Fitzgerald, Gordan Adamson |
| 07:00–17:00 | First site office | Pour plan | Aldo Heikki |
| 07:00–17:00 | First site office | Core and Level 1 drawings | Drakon Niemec |
| 07:00–17:00 | Tower A footprint | Check the bottom mat as it is fixed | Baharata Goretti |
| 07:00–17:00 | Tower B footprint | Excavation monitoring | Alex Markov |
| 07:00–17:00 | Drop Zone | Daytime deliveries | Ben Clarke |
| 07:00–17:00 | The plot | Welfare, water and power | Graham Andaluse |
| 14:00–15:00 | Tower A footprint | Bottom mat reinforcement | Jorge Ramirez, Toshiro Yamamoto, Marcus Oluwaseun, Hassan Mohammed, Jonathan Burgess |
| 15:00–16:30 | The plot | A hot wind off the plain drives sand across the site; work stops, the reinforcement and membrane are covered and loose sheets weighted down | Cary Parsons, Sarah Chen, with everyone on Shift B |
| 16:30–22:00 | Tower A footprint | Sweep the sand off the membrane; bottom mat complete; begin the top mat supports | Jorge Ramirez, Toshiro Yamamoto, Marcus Oluwaseun, Hassan Mohammed, Jonathan Burgess |
| 16:30–22:00 | Tower A footprint | Clean and repair the membrane upstands after the wind | Johann van der Merwe, Nguyen Thanh |
| 16:30–22:00 | Tower A footprint | Edge formwork checks after the wind | Igor Volkov |
| 16:30–22:00 | Tower A footprint | Run the pump on water through both lines | Kofi Adebayo |
| 16:30–22:00 | Tower B footprint | Rip and push spoil | Gus Luciano, Rajesh Kumar, Jed Quintero |
| 16:30–22:00 | Tower B footprint | Level checks | Jonas Hansen |
| 14:00–22:00 | The plot | Supervision; safety | Cary Parsons, Sarah Chen |
| 22:00–06:00 | Tower A footprint | Top mat supports and the first top mat bars | Piotr Nowak, Giovanni Esposito, Miguel Hernandez |
| 22:00–06:00 | Drop Zone | Night deliveries | Rangi Parata |
| 22:00–06:00 | The plot | Supervision; safety | Jake Boyd, Grace Asante |
Sunday 21 October 2018 – The Tower A mat is ready
Rest day: Ben Clarke, Jack Riley. Graham Andaluse takes the daytime deliveries; Guy Barton stockpiles the Tower B spoil at the edge of the dig.
| Time | Where | What | Who |
| 06:00–14:00 | Tower A footprint | Top mat reinforcement | Brad Woodham, Joel Watson, John Slate, Kenneth Richards, Andrei Volkov |
| 06:00–14:00 | Tower A footprint | Cast-in items and starter bars for the cores | Bjorn Andersson, Dmitri Sokolov |
| 06:00–14:00 | Tower A footprint | Final membrane checks and repairs | Marco Bianchi, Rashid Khalil |
| 06:00–11:00 | Tower B footprint | Excavation; spoil stockpiled at the edge | Guy Barton, Winston Obadele, Samuel Mensah |
| 11:00–14:00 | Tower B footprint | Trimming | Guy Barton, Winston Obadele, Samuel Mensah |
| 06:00–14:00 | Tower A footprint | Survey of the top mat levels and the core starter positions | Benny Wong, Carlos Mendoza |
| 06:00–14:00 | Tower A footprint | Sump and drainage; clean the mat of debris | Peter Mahoney, Hernando Rodriguez |
| 06:00–14:00 | Testing room cabin | Test equipment ready for the pour | Olivia Santos |
| 06:00–14:00 | The plot | Supervision; safety | Percy Riall, Marcus Torres |
| 07:00–17:00 | The plot | Site walk and management | Archibald Beulen |
| 07:00–14:00 | First site office | Costs and progress | Samantha Greenfield |
| 07:00–17:00 | First site office | Records; worker lists for every hour of the pour | Thomas Fitzgerald, Gordan Adamson |
| 07:00–14:00 | First site office | Pour plan | Aldo Heikki |
| 07:00–17:00 | First site office | Core drawings | Drakon Niemec |
| 07:00–17:00 | Tower B footprint | Excavation monitoring | Alex Markov |
| 07:00–17:00 | First site office | Orders and costs; confirm the concrete booking with Killerton | Fyodor Das |
| 07:00–17:00 | Drop Zone | Daytime deliveries | Graham Andaluse |
| 07:00–17:00 | Astra Grantley portal | Check the hopper and line connection; service the trucks for the mat pour | Teodora Ilieva, Femi Oyelaran, Ruairi Doyle, Valentina Cruz |
| 07:00–14:00 | Tower A footprint | Check the top mat as it is fixed | Baharata Goretti, Barry Zigmund |
| 14:00–16:00 | Tower A footprint | Final reinforcement inspection: Baharata Goretti asks for extra ties at two laps in the north-west corner before she will sign it off | Baharata Goretti, Barry Zigmund, Brad Woodham, Jorge Ramirez |
| 16:00–17:30 | First site office | Pre-pour briefing for the Tower A mat | Archibald Beulen, Samantha Greenfield, Aldo Heikki, Brad Woodham, Jorge Ramirez, Kofi Adebayo, Olivia Santos, Barry Zigmund, Baharata Goretti, Cary Parsons, Sarah Chen, Teodora Ilieva |
| 14:00–16:00 | Tower A footprint | Top mat reinforcement | Toshiro Yamamoto, Marcus Oluwaseun, Hassan Mohammed, Jonathan Burgess |
| 16:00–22:00 | Tower A footprint | Extra ties at the north-west laps; top mat complete | Jorge Ramirez, Toshiro Yamamoto, Marcus Oluwaseun, Hassan Mohammed, Jonathan Burgess |
| 14:00–22:00 | Tower A footprint | Final membrane upstands | Johann van der Merwe, Nguyen Thanh |
| 14:00–22:00 | Tower A footprint | Edge formwork and stop-ends | Igor Volkov |
| 14:00–16:00 | Tower A footprint | Final check of both pump lines | Kofi Adebayo |
| 14:00–22:00 | Tower B footprint | Rip and push spoil | Gus Luciano, Rajesh Kumar, Jed Quintero |
| 14:00–22:00 | Tower B footprint | Level checks | Jonas Hansen |
| 14:00–22:00 | Tower A footprint | Lighting for the overnight pour | Ahmed Khalil |
| 14:00–16:00 | The plot | Supervision; safety | Cary Parsons, Sarah Chen |
| 17:30–22:00 | The plot | Supervision; safety | Cary Parsons, Sarah Chen |
| 22:00–06:00 | Tower A footprint | Clean the mat and blow out debris before the pour | Piotr Nowak, Giovanni Esposito |
| 22:00–06:00 | Tower B footprint | Excavation under lights | Dmitri Volkov, Miguel Hernandez |
| 22:00–06:00 | Drop Zone | Night deliveries | Rangi Parata |
| 22:00–06:00 | The plot | Supervision; safety | Jake Boyd, Grace Asante |