The Arlington – Construction Programme, Week 2 (8–14 October 2018)
The day-by-day, shift-by-shift working programme for The Arlington's second week, 8 to 14 October 2018, when the Tower A excavation began on all three shifts, the ground proved harder than expected and the heaviest breaking moved to the cool of the morning and the night. It records who was on site each day, who started, who was on a rest day, and what each person was doing on each shift, from the first bucket of the dig to the rebar and formwork yard taking shape for the first foundation mat.
The day-by-day, shift-by-shift working programme for The Arlington in Project Week 2, Monday 8 to Sunday 14 October 2018: the week the Tower A excavation began, the ground proved harder than expected, and the concrete and formwork crews set up for the first foundation mat. Each row is one piece of work on one day, in one place, by the people named, and each row is written up as its own event. Anyone not listed on a shift was not working.
How to read the programme
- Shifts: Shift A 06:00–14:00 (Percy Riall), Shift B 14:00–22:00 (Cary Parsons), Shift C 22:00–06:00 (Jake Boyd). Day means management, design, planning and office staff, 07:00–17:00. A Shift C row belongs to the date on which the shift starts.
- Starting on site: each new starter began with a site induction from Marcus Torres (Shift A) or Sarah Chen (Shift B and Shift C) before joining their crew.
- Rest days: everyone works six shifts in seven, with rest days given week by week around the work. This week the seventeen people who started on site between 28 September and 1 October each took their first rest day. Those who started from 4 October onwards took theirs from Week 3.
- Cover: when a shift supervisor was on a rest day, Fyodor Das ran the shift in their place.
- Places: the plot is the whole site in District 8. The Drop Zone is the open ground near the portals, separate from them, where deliveries from Earth were set down and received, about three kilometres from the site.
- Times within a shift are approximate unless stated.
On site during the week
| Date | On site | Starting on site | Rest day |
| Mon 8 Oct | 38 | Carlos Mendoza, Peter Mahoney, Brad Woodham, Joel Watson, John Slate, Bjorn Andersson (Shift A); Jonas Hansen, Jonathan Burgess, Ahmed Khalil (Shift B); Rangi Parata (Shift C) | – |
| Tue 9 Oct | 35 | – | Drakon Niemec, Gordan Adamson, Fyodor Das |
| Wed 10 Oct | 35 | – | Graham Andaluse, Barry Zigmund, Cary Parsons |
| Thu 11 Oct | 35 | – | Archibald Beulen, Thomas Fitzgerald, Hernando Rodriguez |
| Fri 12 Oct | 35 | – | Aldo Heikki, Benny Wong, Ben Clarke |
| Sat 13 Oct | 36 | – | Percy Riall, Baharata Goretti |
| Sun 14 Oct | 35 | – | Samantha Greenfield, Alex Markov, Marcus Torres |
Crews this week
| Shift | Work | People |
| Day | Management, design, planning, records, quality, logistics | Archibald Beulen, Samantha Greenfield, Thomas Fitzgerald, Aldo Heikki, Drakon Niemec, Baharata Goretti, Alex Markov, Ben Clarke, Fyodor Das, Gordan Adamson, Graham Andaluse, Barry Zigmund |
| Shift A | Supervision and safety | Percy Riall, Marcus Torres |
| Shift A | Tower A excavation | Guy Barton (excavator), Jack Riley (loader), Winston Obadele and Samuel Mensah (banksmen, edge protection) |
| Shift A | Survey and civil | Benny Wong, Carlos Mendoza, Hernando Rodriguez, Peter Mahoney |
| Shift A | Rebar and formwork yard | Brad Woodham, Joel Watson, John Slate, Bjorn Andersson |
| Shift B | Supervision and safety | Cary Parsons, Sarah Chen |
| Shift B | Tower A excavation | Gus Luciano (dozer), Rajesh Kumar and Jed Quintero (banksmen, spoil) |
| Shift B | Survey, rebar, temporary power | Jonas Hansen, Jonathan Burgess, Ahmed Khalil |
| Shift C | Supervision, excavation, receiving | Jake Boyd, Dmitri Volkov (excavator), Miguel Hernandez (banksman), Rangi Parata (night receiving at the Drop Zone) |
Monday 8 October 2018 – Tower A excavation begins
| Time | Where | What | Who |
| 06:00–06:30 | Tower A footprint | The first bucket of the Tower A excavation, at the north-east corner | Guy Barton, watched by Archibald Beulen, Aldo Heikki, Alex Markov, Percy Riall |
| 06:00–07:30 | First site office | Starters' induction | Carlos Mendoza, Peter Mahoney, Brad Woodham, Joel Watson, John Slate, Bjorn Andersson; inducted by Marcus Torres |
| 06:30–14:00 | Tower A footprint | Excavation; spoil loaded and carried to the spoil area | Guy Barton, Jack Riley, Winston Obadele, Samuel Mensah |
| 06:00–14:00 | Tower A footprint | Level checks on the dig every hour | Benny Wong; Carlos Mendoza from 07:30 |
| 07:30–14:00 | The plot | Set out the route of the temporary water main to the cabins | Peter Mahoney, Hernando Rodriguez |
| 07:30–14:00 | Laydown area 2 | Set up the rebar and formwork yard: bending bench, cutting station, stacking bays | Brad Woodham, Joel Watson, John Slate, Bjorn Andersson |
| 07:30–14:00 | The plot | Supervision; safety walk | Percy Riall, Marcus Torres |
| 07:00–12:00 | Tower A footprint | Watch the ground as it opens: a hard, cemented layer about a metre down | Alex Markov |
| 13:00–14:30 | First site office | The mat rebar schedules: Brad Woodham finds bar marks that do not match the drawings, and Baharata Goretti takes it badly | Baharata Goretti, Brad Woodham |
| 07:00–17:00 | First site office | Orders for the Tower A mat: membrane, rebar, formwork; first booking of concrete with Killerton | Fyodor Das, Samantha Greenfield |
| 07:00–17:00 | First site office | Worker files for the ten starters; daily diary | Thomas Fitzgerald, Gordan Adamson |
| 07:00–17:00 | First site office | Inspection and test plan for the excavation and the mat | Barry Zigmund |
| 07:00–17:00 | Drop Zone | Daytime deliveries: fuel, water, formwork timber | Ben Clarke |
| 07:00–17:00 | Bixbus | Press Bixbus again for more site power | Graham Andaluse |
| 07:00–17:00 | First site office | Core and Level 1 drawings | Drakon Niemec |
| 07:00–17:00 | First site office | Programme and look-ahead | Aldo Heikki, Archibald Beulen |
| 14:00–15:30 | First site office | Starters' induction | Jonas Hansen, Jonathan Burgess, Ahmed Khalil; inducted by Sarah Chen |
| 14:00–22:00 | Tower A footprint | Rip the hard layer with the dozer and push spoil to the loading point | Gus Luciano, Rajesh Kumar, Jed Quintero |
| 15:30–22:00 | Tower A footprint | Level checks | Jonas Hansen |
| 15:30–22:00 | Laydown area 2 | Sort and stack the first formwork timber | Jonathan Burgess |
| 15:30–22:00 | Plot boundary | Survey the boundary power connection; plan the site distribution | Ahmed Khalil |
| 14:00–22:00 | The plot | Supervision; safety walk | Cary Parsons, Sarah Chen |
| 21:00–22:00 | First site office | Starter's induction | Rangi Parata; inducted by Sarah Chen |
| 22:00–06:00 | Tower A footprint | Excavation under lights | Dmitri Volkov, Miguel Hernandez |
| 22:00–06:00 | Drop Zone | First night receiving deliveries at the Drop Zone | Rangi Parata |
| 22:00–06:00 | The plot | Supervision; security | Jake Boyd |
Tuesday 9 October 2018
Rest day: Drakon Niemec, Gordan Adamson, Fyodor Das.
| Time | Where | What | Who |
| 07:00–08:30 | Drop Zone | Receive the heavier hydraulic breaker attachments from Killerton | Ben Clarke |
| 06:00–09:30 | Tower A footprint | Excavation; from 09:30, fit the first breaker attachment to the excavator | Guy Barton, Jack Riley |
| 09:30–14:00 | Tower A footprint | Break out the hard layer and load the spoil | Guy Barton, Jack Riley, Winston Obadele |
| 11:30–13:00 | Tower A footprint | Guy Barton's excavator overheats in the midday sun and is stood down | Guy Barton, Percy Riall, Marcus Torres, Alex Markov |
| 06:00–14:00 | Tower A footprint | Level checks | Benny Wong, Carlos Mendoza |
| 06:00–14:00 | The plot | Hand-dig the trench for the temporary water main | Peter Mahoney, Samuel Mensah, Hernando Rodriguez |
| 06:00–14:00 | Laydown area 2 | Finish the rebar yard; begin the mat edge formwork panels | Brad Woodham, Joel Watson, John Slate, Bjorn Andersson |
| 06:00–14:00 | The plot | Supervision; safety | Percy Riall, Marcus Torres |
| 13:00–14:00 | First site office | Move the heaviest breaking to the early morning and the night shift | Alex Markov, Aldo Heikki, Percy Riall |
| 07:00–17:00 | The plot | Site walk and management | Archibald Beulen |
| 07:00–17:00 | First site office | Costs and progress report for Killerton | Samantha Greenfield |
| 07:00–17:00 | First site office | Records and daily diary | Thomas Fitzgerald |
| 07:00–17:00 | First site office | Correct the mat rebar schedules | Baharata Goretti |
| 07:00–17:00 | First site office | Quality records for the excavation | Barry Zigmund |
| 07:00–17:00 | The plot | Welfare, water and power | Graham Andaluse |
| 08:30–17:00 | Drop Zone | Daytime deliveries | Ben Clarke |
| 14:00–22:00 | Tower A footprint | Rip and push spoil | Gus Luciano, Rajesh Kumar |
| 14:00–22:00 | Plot boundary | Install the main temporary distribution board at the boundary connection | Ahmed Khalil, Jed Quintero |
| 14:00–22:00 | Tower A footprint | Level checks | Jonas Hansen |
| 14:00–22:00 | Laydown area 2 | Formwork panels | Jonathan Burgess |
| 14:00–22:00 | The plot | Supervision; safety | Cary Parsons, Sarah Chen |
| 22:00–06:00 | Tower A footprint | Heavy breaking and excavation in the cool of the night | Dmitri Volkov, Miguel Hernandez |
| 22:00–06:00 | Drop Zone | Night deliveries | Rangi Parata |
| 22:00–06:00 | The plot | Supervision; security | Jake Boyd |
Wednesday 10 October 2018
Rest day: Graham Andaluse, Barry Zigmund, Cary Parsons. Fyodor Das runs Shift B.
| Time | Where | What | Who |
| 06:00–10:30 | Tower A footprint | Heavy breaking in the cooler morning | Guy Barton, Winston Obadele, Samuel Mensah |
| 10:30–14:00 | Tower A footprint | Loading and light trimming only | Guy Barton, Winston Obadele, Samuel Mensah |
| 06:00–14:00 | Tower A footprint | Level checks; the north half reaches two metres | Benny Wong, Carlos Mendoza |
| 06:00–14:00 | The plot | Lay the temporary water main; connect the welfare cabin | Peter Mahoney, Hernando Rodriguez |
| 07:00–09:00 | Drop Zone | The first rebar for the Tower A mat arrives: one bundle short on the delivery note | Ben Clarke |
| 09:00–12:00 | Laydown area 2 | Unload the rebar with the telehandler | Jack Riley, Brad Woodham |
| 06:00–09:00 | Tower A footprint | Load spoil | Jack Riley |
| 12:00–14:00 | Tower A footprint | Load spoil | Jack Riley |
| 06:00–14:00 | Laydown area 2 | Check, tag and stack the rebar against the corrected schedules; edge formwork | Brad Woodham, Joel Watson, John Slate, Bjorn Andersson |
| 06:00–14:00 | The plot | Supervision; safety | Percy Riall, Marcus Torres |
| 07:00–17:00 | The plot | Site walk and management | Archibald Beulen |
| 07:00–17:00 | First site office | Chase Killerton for the missing rebar bundle | Samantha Greenfield |
| 07:00–17:00 | First site office | Records and daily diary | Thomas Fitzgerald, Gordan Adamson |
| 07:00–17:00 | First site office | Programme | Aldo Heikki |
| 07:00–17:00 | First site office | Core and Level 1 drawings | Drakon Niemec |
| 07:00–17:00 | First site office | Mat design checks | Baharata Goretti |
| 07:00–17:00 | Tower A footprint | Excavation monitoring | Alex Markov |
| 09:00–17:00 | Drop Zone | Daytime deliveries | Ben Clarke |
| 07:00–13:00 | First site office | Orders and costs | Fyodor Das |
| 14:00–22:00 | The plot | Runs Shift B in place of Cary Parsons | Fyodor Das |
| 14:00–22:00 | Tower A footprint | Rip and push spoil | Gus Luciano, Rajesh Kumar, Jed Quintero |
| 14:00–22:00 | First site office | Cable power from the distribution board to the site office | Ahmed Khalil |
| 14:00–22:00 | Tower A footprint | Level checks | Jonas Hansen |
| 14:00–22:00 | Laydown area 2 | Rebar stacking | Jonathan Burgess |
| 14:00–22:00 | The plot | Safety walk | Sarah Chen |
| 22:00–06:00 | Tower A footprint | Heavy breaking and excavation | Dmitri Volkov, Miguel Hernandez |
| 22:00–06:00 | Drop Zone | Night deliveries, including the missing rebar bundle | Rangi Parata |
| 22:00–06:00 | The plot | Supervision; security | Jake Boyd |
Thursday 11 October 2018
Rest day: Archibald Beulen, Thomas Fitzgerald, Hernando Rodriguez.
| Time | Where | What | Who |
| 06:00–10:30 | Tower A footprint | Heavy breaking | Guy Barton, Jack Riley, Winston Obadele, Samuel Mensah |
| 10:30–14:00 | Tower A footprint | Loading and trimming | Guy Barton, Jack Riley, Winston Obadele, Samuel Mensah |
| 06:00–14:00 | Tower A footprint | Level checks | Benny Wong, Carlos Mendoza |
| 06:00–10:00 | The plot | Water main to the store and second welfare cabin | Peter Mahoney |
| 10:00–14:00 | Tower A footprint | Set out the drainage sump at the low corner of the dig | Peter Mahoney |
| 06:00–14:00 | Laydown area 2 | Cut and bend the first bars for the bottom mat; edge formwork | Brad Woodham, Joel Watson, John Slate, Bjorn Andersson |
| 06:00–14:00 | The plot | Supervision; safety | Percy Riall, Marcus Torres |
| 09:00–11:00 | First site office | Programme review: the Tower A dig is a day and a half behind because of the hard ground | Samantha Greenfield, Aldo Heikki, Alex Markov, Baharata Goretti |
| 07:00–17:00 | First site office | Records and daily diary | Gordan Adamson |
| 07:00–17:00 | First site office | Quality records | Barry Zigmund |
| 07:00–17:00 | First site office | Orders and costs | Fyodor Das |
| 07:00–17:00 | The plot | Welfare, water and power | Graham Andaluse |
| 07:00–17:00 | First site office | Core and Level 1 drawings | Drakon Niemec |
| 07:00–17:00 | Drop Zone | Daytime deliveries | Ben Clarke |
| 14:00–22:00 | Tower A footprint | Rip and push spoil | Gus Luciano, Rajesh Kumar, Jed Quintero |
| 15:30–16:30 | Welfare cabin | Rajesh Kumar is dizzy and sick in the afternoon heat; Sarah Chen sends him to the welfare cabin to cool down and stands him down for the rest of the shift | Rajesh Kumar, Sarah Chen |
| 14:00–22:00 | Welfare cabins | Power to the welfare cabins | Ahmed Khalil |
| 14:00–22:00 | Tower A footprint | Level checks | Jonas Hansen |
| 14:00–22:00 | Laydown area 2 | Bending | Jonathan Burgess |
| 14:00–22:00 | The plot | Supervision; safety | Cary Parsons, Sarah Chen |
| 22:00–06:00 | Tower A footprint | Heavy breaking and excavation | Dmitri Volkov, Miguel Hernandez |
| 22:00–06:00 | Drop Zone | Night deliveries | Rangi Parata |
| 22:00–06:00 | The plot | Supervision; security | Jake Boyd |
Friday 12 October 2018
Rest day: Aldo Heikki, Benny Wong, Ben Clarke. Carlos Mendoza leads the Shift A survey; Graham Andaluse takes the daytime deliveries.
| Time | Where | What | Who |
| 06:00–10:30 | Tower A footprint | Heavy breaking; the east side reaches three metres | Guy Barton, Samuel Mensah |
| 10:30–14:00 | Tower A footprint | Loading and trimming | Guy Barton, Samuel Mensah |
| 06:00–14:00 | Tower A footprint | Edge protection and shoring panels along the deepest edge | Hernando Rodriguez, Winston Obadele |
| 06:00–14:00 | Tower A footprint | Level checks | Carlos Mendoza |
| 06:00–14:00 | Tower A footprint | Dig the drainage sump and set the first pump | Peter Mahoney |
| 06:00–14:00 | Laydown area 2 | Bending; edge formwork | Brad Woodham, Joel Watson, John Slate, Bjorn Andersson |
| 06:00–14:00 | The plot | Supervision; safety | Percy Riall, Marcus Torres |
| 06:00–09:00 | Tower A footprint | Load spoil | Jack Riley |
| 09:00–11:00 | Drop Zone | Receive the waterproofing membrane rolls for the Tower A mat | Graham Andaluse |
| 11:00–12:30 | Laydown area 1 | Unload and store the membrane rolls | Jack Riley, Graham Andaluse |
| 12:30–14:00 | Tower A footprint | Load spoil | Jack Riley |
| 12:30–17:00 | Drop Zone | Daytime deliveries | Graham Andaluse |
| 07:00–17:00 | The plot | Site walk and management | Archibald Beulen |
| 07:00–17:00 | First site office | Costs and progress | Samantha Greenfield |
| 07:00–17:00 | First site office | Records and daily diary | Thomas Fitzgerald, Gordan Adamson |
| 07:00–17:00 | First site office | Orders and costs | Fyodor Das |
| 07:00–17:00 | First site office | Quality records | Barry Zigmund |
| 07:00–17:00 | First site office | Core and Level 1 drawings | Drakon Niemec |
| 07:00–17:00 | First site office | Mat design checks | Baharata Goretti |
| 07:00–17:00 | Tower A footprint | Excavation monitoring | Alex Markov |
| 14:00–22:00 | Tower A footprint | Rip and push spoil | Gus Luciano, Rajesh Kumar, Jed Quintero |
| 14:00–22:00 | Laydown areas | The first mains-powered floodlights replace two of the lighting towers | Ahmed Khalil |
| 14:00–22:00 | Tower A footprint | Level checks | Jonas Hansen |
| 14:00–22:00 | Laydown area 2 | Bending | Jonathan Burgess |
| 14:00–22:00 | The plot | Supervision; safety | Cary Parsons, Sarah Chen |
| 22:00–06:00 | Tower A footprint | Heavy breaking and excavation | Dmitri Volkov, Miguel Hernandez |
| 22:00–06:00 | Drop Zone | Night deliveries | Rangi Parata |
| 22:00–06:00 | The plot | Supervision; security | Jake Boyd |
Saturday 13 October 2018
Rest day: Percy Riall, Baharata Goretti. Fyodor Das runs Shift A.
| Time | Where | What | Who |
| 06:00–10:00 | Tower A footprint | Heavy breaking; the east bay reaches formation level, 3.5 metres below grade | Guy Barton, Jack Riley, Winston Obadele, Samuel Mensah |
| 06:00–10:00 | Tower A footprint | Survey of the east bay formation | Benny Wong, Carlos Mendoza |
| 10:00–12:00 | Tower A footprint | First inspection of the east bay formation: Barry Zigmund rejects a strip of loose material along the south edge and asks for it to be dug out again. Guy Barton argues it is sound | Barry Zigmund, Alex Markov, Hernando Rodriguez, Guy Barton |
| 12:00–14:00 | Tower A footprint | Dig out and trim the rejected strip | Guy Barton, Jack Riley, Winston Obadele, Samuel Mensah |
| 10:00–14:00 | Tower A footprint | Level checks | Benny Wong, Carlos Mendoza |
| 06:00–10:00 | Tower A footprint | Sump pumping; shoring along the east edge | Peter Mahoney, Hernando Rodriguez |
| 12:00–14:00 | Tower A footprint | Sump pumping | Peter Mahoney, Hernando Rodriguez |
| 06:00–14:00 | Laydown area 2 | Begin pre-tying bottom mat bars in the yard | Brad Woodham, Joel Watson, John Slate, Bjorn Andersson |
| 06:00–14:00 | The plot | Runs Shift A in place of Percy Riall | Fyodor Das |
| 06:00–14:00 | The plot | Safety walk | Marcus Torres |
| 07:00–17:00 | The plot | Site walk and management | Archibald Beulen |
| 07:00–17:00 | First site office | Costs and progress | Samantha Greenfield |
| 07:00–17:00 | First site office | Records and daily diary | Thomas Fitzgerald, Gordan Adamson |
| 07:00–17:00 | First site office | Programme | Aldo Heikki |
| 07:00–17:00 | First site office | Core and Level 1 drawings | Drakon Niemec |
| 07:00–17:00 | Drop Zone | Daytime deliveries | Ben Clarke |
| 07:00–17:00 | The plot | Welfare, water and power | Graham Andaluse |
| 12:00–17:00 | First site office | Write up the formation inspection | Barry Zigmund, Alex Markov |
| 14:00–22:00 | Tower A footprint | Rip and push spoil | Gus Luciano, Rajesh Kumar, Jed Quintero |
| 14:00–22:00 | The plot | More floodlights onto mains power | Ahmed Khalil |
| 14:00–22:00 | Tower A footprint | Level checks | Jonas Hansen |
| 14:00–22:00 | Laydown area 2 | Pre-tying | Jonathan Burgess |
| 14:00–22:00 | The plot | Supervision; safety | Cary Parsons, Sarah Chen |
| 22:00–06:00 | Tower A footprint | Heavy breaking and excavation | Dmitri Volkov, Miguel Hernandez |
| 22:00–06:00 | Drop Zone | Night deliveries | Rangi Parata |
| 22:00–06:00 | The plot | Supervision; security | Jake Boyd |
Sunday 14 October 2018
Rest day: Samantha Greenfield, Alex Markov, Marcus Torres. Hernando Rodriguez leads the excavation checks; Percy Riall covers safety on Shift A.
| Time | Where | What | Who |
| 06:00–10:30 | Tower A footprint | Heavy breaking; about two-thirds of the footprint is now at formation level | Guy Barton, Jack Riley, Winston Obadele, Samuel Mensah |
| 10:30–14:00 | Tower A footprint | Loading and trimming | Guy Barton, Jack Riley, Winston Obadele, Samuel Mensah |
| 06:00–14:00 | Tower A footprint | Level checks | Benny Wong, Carlos Mendoza |
| 06:00–13:00 | Tower A footprint | Excavation checks | Hernando Rodriguez |
| 06:00–14:00 | Tower A footprint | Sump pumping; trim the east bay formation by hand | Peter Mahoney |
| 06:00–13:00 | Laydown area 2 | Pre-tying; edge formwork complete for the east side | Brad Woodham, Joel Watson, John Slate, Bjorn Andersson |
| 06:00–14:00 | The plot | Supervision; safety | Percy Riall |
| 07:00–13:00 | First site office | Records and daily diary | Thomas Fitzgerald, Gordan Adamson |
| 07:00–13:00 | First site office | Programme | Aldo Heikki |
| 07:00–13:00 | First site office | Orders and costs | Fyodor Das |
| 07:00–13:00 | First site office | Mat design checks | Baharata Goretti |
| 07:00–13:00 | The plot | Site walk | Archibald Beulen |
| 07:00–13:00 | First site office | Quality records | Barry Zigmund |
| 13:00–15:00 | First site office | Week 3 look-ahead: finish the Tower A dig, start Tower B, membrane under the Tower A mat, the crews starting on Monday | Archibald Beulen, Aldo Heikki, Baharata Goretti, Barry Zigmund, Fyodor Das, Brad Woodham, Hernando Rodriguez |
| 15:00–17:00 | First site office | Pour plan for the Tower A mat on 22 October | Aldo Heikki, Baharata Goretti, Fyodor Das |
| 13:00–17:00 | First site office | Worker files for Monday's seventeen starters | Thomas Fitzgerald, Gordan Adamson |
| 07:00–17:00 | The plot | Welfare cabins for Monday's starters | Graham Andaluse |
| 07:00–17:00 | Drop Zone | Daytime deliveries | Ben Clarke |
| 07:00–17:00 | First site office | Core and Level 1 drawings | Drakon Niemec |
| 15:00–17:00 | The plot | Site walk | Archibald Beulen, Barry Zigmund |
| 14:00–22:00 | Tower A footprint | Rip and push spoil | Gus Luciano, Rajesh Kumar, Jed Quintero |
| 14:00–22:00 | The plot | Site lighting on mains power for the cabins and laydown areas | Ahmed Khalil |
| 14:00–22:00 | Tower A footprint | Level checks | Jonas Hansen |
| 14:00–22:00 | Laydown area 2 | Pre-tying | Jonathan Burgess |
| 14:00–22:00 | The plot | Supervision; safety | Cary Parsons, Sarah Chen |
| 22:00–06:00 | Tower A footprint | Heavy breaking and excavation | Dmitri Volkov, Miguel Hernandez |
| 22:00–06:00 | Drop Zone | Night deliveries | Rangi Parata |
| 22:00–06:00 | The plot | Supervision; security | Jake Boyd |