The Arlington – Construction Programme, Week 1 (28 September – 7 October 2018)
The day-by-day, shift-by-shift working programme for The Arlington's first week, from the leadership team's first day on the plot in District 8 on 28 September 2018 to the evening of 7 October, when the site was fenced, lit and running on all three shifts. It records who was on site each day, who arrived, and what each person was doing on each shift, from the groundbreaking stake to the first night shift.
The day-by-day, shift-by-shift working programme for The Arlington in Project Week 1, from the leadership team's first day on the plot on Friday 28 September 2018 to the evening of Sunday 7 October, when the site was fenced, lit and running on all three shifts. Each row is one piece of work on one day, in one place, by the people named, and each row is written up as its own event. Anyone not listed on a shift was not working.
How to read the programme
- Shifts: Shift A 06:00–14:00 (Percy Riall), Shift B 14:00–22:00 (Cary Parsons), Shift C 22:00–06:00 (Jake Boyd). Day means management, design, planning and office staff, who worked 07:00–17:00.
- Starting on site: each new starter began with a site induction from Marcus Torres (Shift A and Day staff) or Sarah Chen (Shift B, from 5 October), before going to their crew.
- Rest days: everyone works six shifts in seven. Rest days are not fixed: they are given week by week, around the work that needs doing, and each day lists who is off. Nobody took a rest day in Week 1.
- Places: the plot is the whole site in District 8. The Drop Zone is the open ground near the portals, separate from them, where deliveries from Earth were set down and received, about three kilometres from the site.
- Times within a shift are approximate unless stated.
On site during the week
| Date | On site | Starting on site |
| Fri 28 Sep | 9 | Archibald Beulen, Samantha Greenfield, Marcus Torres, Thomas Fitzgerald, Drakon Niemec, Baharata Goretti, Alex Markov, Aldo Heikki, Benny Wong |
| Sat 29 Sep | 9 | – |
| Sun 30 Sep | 12 | Ben Clarke, Percy Riall, Cary Parsons |
| Mon 1 Oct | 17 | Fyodor Das, Gordan Adamson, Graham Andaluse, Barry Zigmund, Hernando Rodriguez |
| Tue 2 Oct | 17 | – |
| Wed 3 Oct | 17 | – |
| Thu 4 Oct | 27 | Jake Boyd; Guy Barton, Gus Luciano, Dmitri Volkov, Jack Riley; Winston Obadele, Rajesh Kumar, Miguel Hernandez, Samuel Mensah, Jed Quintero |
| Fri 5 Oct | 28 | Sarah Chen |
| Sat 6 Oct | 28 | – |
| Sun 7 Oct | 28 | – |
Crews this week
| Shift | People |
| Day | Archibald Beulen, Samantha Greenfield, Thomas Fitzgerald, Aldo Heikki, Drakon Niemec, Baharata Goretti, Alex Markov, Ben Clarke, Fyodor Das, Gordan Adamson, Graham Andaluse, Barry Zigmund |
| Shift A | Percy Riall, Marcus Torres, Benny Wong, Hernando Rodriguez; from 4 October Guy Barton, Jack Riley, Winston Obadele, Samuel Mensah |
| Shift B | Cary Parsons; from 4 October Gus Luciano, Rajesh Kumar, Jed Quintero; from 5 October Sarah Chen |
| Shift C | From 4 October Jake Boyd, Dmitri Volkov, Miguel Hernandez |
Friday 28 September 2018
The leadership team's first day on the plot in District 8. No construction work.
| Time | Where | What | Who |
| 07:00–08:00 | The plot | First day on site: the nine meet at the plot | Archibald Beulen, Samantha Greenfield, Marcus Torres, Thomas Fitzgerald, Drakon Niemec, Baharata Goretti, Alex Markov, Aldo Heikki, Benny Wong |
| 08:00–12:00 | The plot | First walk of the whole plot, boundary to boundary, and down to the river | All nine, led by Archibald Beulen |
| 13:00–16:00 | The plot | Look at the ground where each tower will stand; first impressions of the surface and soil | Drakon Niemec, Baharata Goretti, Alex Markov |
| 13:00–16:00 | Plot boundary | Walk the boundary and look for the marks left by the Bixbus survey | Benny Wong |
| 13:00–16:00 | The plot | Note the first hazards: heat, sun, loose sand, the river bank | Marcus Torres |
| 13:00–16:00 | The plot | Choose where the site office, stores and welfare cabins will go | Thomas Fitzgerald, Samantha Greenfield |
| 13:00–16:00 | The plot | Compare the baseline programme with the ground | Aldo Heikki, Archibald Beulen |
| 16:00–17:00 | The plot | First briefing in the open: who arrives when, and what has to be ready by Monday | All nine, led by Archibald Beulen |
Saturday 29 September 2018
Planning on the ground. No construction work.
| Time | Where | What | Who |
| 07:00–17:00 | The plot | Check the plot boundary and plan the primary survey control network | Benny Wong, Alex Markov |
| 07:00–17:00 | The plot | Check the tower positions and the courtyard between them against the ground | Drakon Niemec, Baharata Goretti |
| 07:00–17:00 | The plot | Draft the site safety plan; heat, sun and sand come first | Marcus Torres |
| 07:00–12:00 | The plot | Draw up the layout of cabins, stores and welfare | Thomas Fitzgerald, Samantha Greenfield |
| 13:00–17:00 | The plot | Set up the first paper records: who is on site, what is due | Thomas Fitzgerald |
| 07:00–17:00 | The plot | Rework the first two weeks of the baseline programme for what the ground looks like | Aldo Heikki |
| 13:00–16:00 | Drop Zone | Meet the Guardians to agree how deliveries through the five portals will be brought to the Drop Zone; a sharp exchange over how much notice the Guardians need before each opening | Archibald Beulen, Samantha Greenfield |
Sunday 30 September 2018
The two shift supervisors and the logistics coordinator start on site.
| Time | Where | What | Who |
| 07:00–08:00 | The plot | First day on site | Ben Clarke, Percy Riall, Cary Parsons |
| 08:00–11:00 | The plot | Walk the plot with the Project Director | Ben Clarke, Percy Riall, Cary Parsons, Archibald Beulen |
| 13:00–16:00 | Drop Zone | Walk the Drop Zone and agree how deliveries will be booked, received and logged | Ben Clarke, Samantha Greenfield |
| 13:00–16:00 | The plot | Set out the fence line, gates, laydown areas and the site of the first cabins | Percy Riall, Cary Parsons, Marcus Torres |
| 07:00–16:00 | The plot | Mark the positions of the survey control monuments | Benny Wong, Alex Markov |
| 07:00–16:00 | The plot | Check the foundation drawings against the tower positions | Drakon Niemec, Baharata Goretti |
| 07:00–16:00 | The plot | Prepare the personnel and delivery records for Monday | Thomas Fitzgerald |
| 07:00–16:00 | The plot | Programme for Week 1 | Aldo Heikki |
| 16:00–17:00 | The plot | Week 1 briefing: the shift pattern, the first deliveries, and the plan for Monday | All twelve, led by Archibald Beulen and Aldo Heikki |
Monday 1 October 2018 – Groundbreaking
The first working day. Day staff and Shift A in the morning; the first Shift B from 14:00. No night shift yet.
| Time | Where | What | Who |
| 06:00–06:30 | The plot | Groundbreaking: the first reference stake of the survey control network | Benny Wong drives the stake; Archibald Beulen, Samantha Greenfield, Percy Riall, Marcus Torres, Alex Markov, Drakon Niemec, Baharata Goretti, Aldo Heikki, Thomas Fitzgerald present |
| 06:30–14:00 | The plot | Set the primary survey control monuments around the plot | Benny Wong, Alex Markov |
| 07:00–08:30 | The plot | Starters' induction | Fyodor Das, Gordan Adamson, Graham Andaluse, Barry Zigmund, Hernando Rodriguez; inducted by Marcus Torres |
| 08:30–12:00 | The plot | Site hazard walk and the first hazard log | Marcus Torres |
| 08:00–14:00 | Drop Zone | Receive the first deliveries: flat-pack site office and store cabins, hand tools, water | Ben Clarke |
| 09:00–14:00 | The plot | Assemble the first site office cabin, by hand | Percy Riall, Hernando Rodriguez, Graham Andaluse |
| 14:00–17:00 | First site office | Open the project records: personnel, deliveries, daily diary | Thomas Fitzgerald, Gordan Adamson |
| 08:30–17:00 | The plot | Set up cost reporting and the orders to Killerton Enterprises for the next three weeks | Fyodor Das, Samantha Greenfield |
| 08:30–17:00 | The plot | Draft the quality plan and choose a spot for the testing room | Barry Zigmund |
| 08:30–17:00 | The plot | Review the foundation drawings against the ground | Baharata Goretti, Drakon Niemec |
| 08:30–17:00 | The plot | Daily planning and the first look-ahead for Week 2 | Aldo Heikki, Archibald Beulen |
| 14:00–17:00 | First site office | Write up the survey control network | Alex Markov |
| 14:00–18:00 | The plot | First Shift B: assemble the store cabin | Cary Parsons |
| 18:00–22:00 | The plot | Receive and stack the evening delivery of fencing panels and posts | Cary Parsons |
Tuesday 2 October 2018
| Time | Where | What | Who |
| 06:00–10:00 | Tower A footprint | Set out the Tower A grid lines from the control network | Benny Wong, Hernando Rodriguez |
| 10:00–14:00 | Tower B footprint | Set out the Tower B grid lines | Benny Wong, Hernando Rodriguez |
| 06:00–14:00 | The plot | Assemble the first welfare cabin: toilets, water, shade | Percy Riall, Graham Andaluse |
| 06:00–14:00 | First site office | Write the site rules, the heat plan and the induction for the crews starting Thursday | Marcus Torres |
| 07:00–17:00 | Tower A footprint | Survey the surface and mark the trial pit positions | Alex Markov |
| 07:00–17:00 | First site office | Final checks on the foundation and structural drawings before excavation | Baharata Goretti, Drakon Niemec |
| 07:00–17:00 | First site office | Delivery log and worker files for Thursday's starters | Thomas Fitzgerald, Gordan Adamson |
| 07:00–17:00 | First site office | Orders and costs; book the plant for Thursday | Fyodor Das |
| 07:00–17:00 | First site office | Quality procedures for earthworks and concrete | Barry Zigmund |
| 07:00–17:00 | Drop Zone | Daytime deliveries | Ben Clarke |
| 14:00–17:00 | Bixbus | Ask Bixbus for site power and water: water is promised for Wednesday, power only in part | Samantha Greenfield, Graham Andaluse |
| 07:00–17:00 | First site office | Programme and Week 2 look-ahead | Aldo Heikki, Archibald Beulen |
| 14:00–22:00 | Fence line | Receive fencing and lighting towers; stack them along the fence line | Cary Parsons |
Wednesday 3 October 2018
| Time | Where | What | Who |
| 06:00–14:00 | Fence line | Start the perimeter fence at the main gate, by hand | Percy Riall, Hernando Rodriguez |
| 06:00–14:00 | The plot | Set out the laydown areas, tool stores and haul road | Benny Wong |
| 06:00–14:00 | The plot | Safety signage, first-aid point and drinking water stations | Marcus Torres |
| 07:00–13:00 | Plot boundary | Bixbus connects water and temporary power at the boundary, at a little under half the power asked for | Graham Andaluse |
| 13:00–14:00 | First site office | The power shortfall: generators kept on until Bixbus can supply more | Archibald Beulen, Samantha Greenfield, Graham Andaluse |
| 07:00–17:00 | First site office | Excavation plan for Tower A: depth, batter, shoring, where the spoil goes | Alex Markov, Baharata Goretti |
| 07:00–17:00 | First site office | Architectural set for the cores and Level 1 | Drakon Niemec |
| 07:00–17:00 | Drop Zone | Daytime deliveries; book Thursday's plant: two excavators, a dozer, a loader and a telehandler | Ben Clarke |
| 07:00–17:00 | First site office | Records and worker files | Thomas Fitzgerald, Gordan Adamson |
| 07:00–17:00 | First site office | Orders and costs | Fyodor Das |
| 07:00–17:00 | First site office | Quality plan | Barry Zigmund |
| 07:00–17:00 | First site office | Programme | Aldo Heikki |
| 14:00–22:00 | Fence line | Carry on with the fence | Cary Parsons |
Thursday 4 October 2018
The first crews start. The plant comes from the Drop Zone and the night shift begins.
| Time | Where | What | Who |
| 06:00–07:30 | First site office | Starters' induction for Shift A | Guy Barton, Jack Riley, Winston Obadele, Samuel Mensah; inducted by Marcus Torres |
| 07:30–10:30 | Drop Zone | Receive the plant from Earth: two excavators, a dozer, a loader and a telehandler | Ben Clarke, Guy Barton, Jack Riley |
| 10:30–12:00 | Drop Zone to the plot | Drive the plant across Bixbus to the site, watched by settlers along the way | Guy Barton, Jack Riley |
| 12:00–14:00 | Laydown area 1 | Strip and level the first laydown area | Guy Barton |
| 12:00–14:00 | The plot | Move fencing and cabins into place with the telehandler | Jack Riley |
| 07:30–14:00 | Fence line | Perimeter fence | Winston Obadele, Samuel Mensah, Percy Riall |
| 06:00–14:00 | Tower A footprint | Check the grid lines and peg the trial pits | Benny Wong, Hernando Rodriguez |
| 14:00–15:30 | First site office | Starters' induction for Shift B | Gus Luciano, Rajesh Kumar, Jed Quintero; inducted by Marcus Torres, who stays late |
| 15:30–22:00 | Haul road | Push out the haul road and the second laydown area | Gus Luciano |
| 15:30–22:00 | Fence line | Perimeter fence; first lighting towers stood up | Rajesh Kumar, Jed Quintero, Cary Parsons |
| 19:30 | Fence line | Jed Quintero cuts his hand on fence wire; dressed at the first-aid point and back on the fence | Jed Quintero, Cary Parsons |
| 07:00–17:00 | First site office | Records and worker files for the ten starters | Thomas Fitzgerald, Gordan Adamson |
| 07:00–17:00 | First site office | Orders, and welfare cabins and water supplies for twenty-seven | Fyodor Das, Graham Andaluse |
| 07:00–17:00 | First site office | Programme and management | Aldo Heikki, Archibald Beulen, Samantha Greenfield |
| 07:00–17:00 | First site office | Quality plan | Barry Zigmund |
| 07:00–17:00 | First site office | Design: foundations, cores and Level 1 | Drakon Niemec, Baharata Goretti, Alex Markov |
| 10:30–17:00 | Drop Zone | Daytime deliveries | Ben Clarke |
| 21:00–22:30 | First site office | Starters' induction and handover from Shift B | Jake Boyd, Dmitri Volkov, Miguel Hernandez; inducted by Marcus Torres; handover from Cary Parsons |
| 22:30–06:00 | The plot | First night shift: site security, lighting towers, receive the night's deliveries | Jake Boyd, Miguel Hernandez |
| 22:30–06:00 | Laydown area 2 | Finish levelling the second laydown area under lights | Dmitri Volkov |
Friday 5 October 2018
| Time | Where | What | Who |
| 06:00–14:00 | Tower A footprint | Dig the trial pits; log the soil profile | Guy Barton, Benny Wong, Hernando Rodriguez, with Alex Markov from 07:00 |
| 06:00–14:00 | Fence line | Perimeter fence: the east and south sides | Winston Obadele, Samuel Mensah, Percy Riall |
| 06:00–14:00 | The plot | Set up the tool stores | Jack Riley |
| 06:00–14:00 | Laydown area 1 | Inspect the plant before excavation starts | Marcus Torres |
| 13:00–15:00 | First site office | Review the trial pits: the ground is harder than the survey suggested. Alex Markov wants more time for the dig; Baharata Goretti will not change the mat design | Alex Markov, Baharata Goretti, Aldo Heikki |
| 07:00–17:00 | First site office | Records | Thomas Fitzgerald, Gordan Adamson |
| 07:00–17:00 | First site office | Orders and costs | Fyodor Das |
| 07:00–17:00 | First site office | Quality plan | Barry Zigmund |
| 07:00–17:00 | First site office | Architectural drawings | Drakon Niemec |
| 07:00–17:00 | Bixbus | Follow up the power supply with Bixbus | Graham Andaluse, Samantha Greenfield |
| 07:00–17:00 | Drop Zone | Daytime deliveries | Ben Clarke |
| 07:00–17:00 | The plot | Site walk and management | Archibald Beulen |
| 14:00–15:00 | First site office | Starter's induction and handover | Sarah Chen, inducted and briefed by Marcus Torres |
| 14:00–22:00 | Fence line | Fence and lighting towers | Rajesh Kumar, Jed Quintero, Cary Parsons |
| 14:00–22:00 | Spoil area | Clear the area where the Tower A spoil will go | Gus Luciano |
| 15:00–22:00 | The plot | First safety walk | Sarah Chen |
| 22:00–06:00 | The plot | Security; night deliveries; fit out the welfare cabin | Jake Boyd, Miguel Hernandez |
| 22:00–06:00 | Haul road | Grade the haul road | Dmitri Volkov |
Saturday 6 October 2018
| Time | Where | What | Who |
| 06:00–14:00 | Fence line | The perimeter fence closes except for the gates | Winston Obadele, Samuel Mensah, Percy Riall |
| 06:00–14:00 | Tower A footprint | Strip the topsoil from the Tower A footprint | Guy Barton |
| 06:00–14:00 | Fuel store | Build the fuel store and bunding | Jack Riley, Marcus Torres |
| 06:00–14:00 | Tower A footprint | Set out the excavation edges for Tower A | Benny Wong, Hernando Rodriguez |
| 07:00–17:00 | First site office | Revise the Tower A excavation plan for the harder ground | Alex Markov, Baharata Goretti |
| 07:00–17:00 | Drop Zone | Arrange heavier breaking attachments with Killerton; daytime deliveries | Ben Clarke |
| 07:00–17:00 | First site office | Records | Thomas Fitzgerald, Gordan Adamson |
| 07:00–17:00 | First site office | Orders and costs | Fyodor Das |
| 07:00–17:00 | First site office | Quality plan | Barry Zigmund |
| 07:00–17:00 | First site office | Architectural drawings | Drakon Niemec |
| 07:00–17:00 | First site office | Programme: move the start of the dig to Monday at 06:00 | Aldo Heikki, Samantha Greenfield |
| 07:00–17:00 | The plot | Welfare, water and power | Graham Andaluse |
| 07:00–17:00 | The plot | Site walk and management | Archibald Beulen |
| 14:00–22:00 | Main gate | Hang the main gate and the deliveries gate | Rajesh Kumar, Jed Quintero, Cary Parsons |
| 14:00–22:00 | Tower B footprint | Strip the topsoil from the Tower B footprint | Gus Luciano |
| 14:00–22:00 | Fence line | Safety walk; check the fence | Sarah Chen |
| 22:00–06:00 | The plot | Security; night deliveries; the last lighting towers | Jake Boyd, Miguel Hernandez |
| 22:00–06:00 | Tower A footprint | Push the stripped topsoil to the spoil area | Dmitri Volkov |
Sunday 7 October 2018 – Site established
By the end of the day the site is fenced and lit, and all three shifts are running.
| Time | Where | What | Who |
| 06:00–10:00 | Fence line | Last fence panels and signs | Winston Obadele, Samuel Mensah, Percy Riall |
| 06:00–10:00 | Laydown area 1 | Daily checks and greasing on the loader and telehandler; lift the last fence panels to the fence line | Jack Riley |
| 10:00–12:00 | Main gate | Jack Riley clips a fence panel beside the main gate with the telehandler; the bent panel is replaced | Jack Riley, Winston Obadele, Samuel Mensah, Percy Riall |
| 06:00–12:00 | Tower A footprint | Prepare the excavator for the dig | Guy Barton |
| 12:00–14:00 | Tower A footprint | Prepare the plant for the Tower A dig | Guy Barton, Jack Riley |
| 06:00–14:00 | The plot | Final site inspection before excavation | Marcus Torres, Hernando Rodriguez |
| 06:00–14:00 | Tower A footprint | Check the excavation set-out | Benny Wong |
| 07:00–13:00 | First site office | Week 2 look-ahead: Tower A excavation from Monday and the starters due that week | Archibald Beulen, Samantha Greenfield, Aldo Heikki, Alex Markov, Baharata Goretti, Drakon Niemec |
| 07:00–17:00 | First site office | Worker files for Monday's starters | Thomas Fitzgerald, Gordan Adamson |
| 07:00–17:00 | First site office | Orders and costs | Fyodor Das |
| 07:00–17:00 | First site office | Inspection and test plan for the excavation | Barry Zigmund |
| 07:00–17:00 | The plot | Welfare, water and power | Graham Andaluse |
| 07:00–13:00 | Drop Zone | Daytime deliveries | Ben Clarke |
| 13:30–14:30 | First site office | All-hands briefing at the A/B handover: the site is established; excavation starts tomorrow | Archibald Beulen, with everyone on Day, Shift A and Shift B |
| 14:30–22:00 | Laydown areas | Tidy the laydown areas; stack materials for Monday | Rajesh Kumar, Jed Quintero, Cary Parsons |
| 14:30–22:00 | Tower B footprint | Finish stripping the Tower B topsoil | Gus Luciano |
| 14:30–22:00 | The plot | Safety walk | Sarah Chen |
| 22:00–06:00 | The plot | Security; night deliveries | Jake Boyd, Miguel Hernandez |
| 22:00–06:00 | Spoil area | Prepare the spoil area for the Tower A dig | Dmitri Volkov |